πŸ³οΈβ€βš§οΈ trans rights are human rights πŸ³οΈβ€βš§οΈ
Theme
◀
▶

Inside the EPA’s $98,000 Jefferson Road Stormwater Case Against Kokosing

Environmental enforcement

Inside the EPA’s $98,000 Jefferson Road Stormwater Case Against Kokosing

Federal and state inspectors cited damaged sediment controls, exposed slopes, concrete outside a washout and an unstabilized area beside Davis Creek. Kokosing signed a proposed settlement without admitting or denying the factual allegations.

South Charleston, West Virginia EPA Docket CWA-03-2026-0078
Clean Water Act

TL;DR

  • The Environmental Protection Agency alleged five categories of stormwater-permit violations at Kokosing Construction Company’s approximately 1.7-mile Jefferson Road widening project.
  • During a May 2024 inspection, EPA personnel reported more than 15 drop inlets with damaged or insufficient protection, along with failing sediment controls, unstable ground and improperly handled concrete.
  • West Virginia inspectors cited several similar control and stabilization problems in March 2025. The state had previously issued Kokosing notices of violation in August 2022 and May 2023.
  • Kokosing reported repairs, mapping changes and repeated reseeding. It certified that it was currently in compliance when it signed the agreement.
  • The company consented to a $98,000 civil penalty but neither admitted nor denied the specific factual allegations.
  • The supplied copy does not establish that the Final Order became effective: the EPA and judicial signature lines are blank, and the agreement calls for public notice before final issuance.

The case documents a basic construction-control problem with a long paper trail: protections meant to keep disturbed soil and construction waste away from drainage routes were repeatedly cited as missing, damaged or inadequately maintained.

Transparency notice: This article relies on the EPA consent-agreement package supplied with this investigation. The agreement attributes the factual allegations to EPA and cites observations by EPA and the West Virginia Department of Environmental Protection. Kokosing admitted jurisdiction only, neither admitted nor denied the specific factual allegations, and waived its right to contest them for this proceeding. The respondent’s signature is dated June 4, 2026, but the supplied EPA signature pages, Final Order and certificate of service do not display completed official signatures or a filing date.

At the Jefferson Road construction site in May 2024, EPA inspectors said they found more than 15 storm-drain inlets with damaged or insufficient protection. Some were inundated with sediment or gravel. Elsewhere, silt fencing was collapsing or overwhelmed, access points lacked enough stone to keep sediment from being tracked onto the road, and concrete had been left outside a designated washout area.

Those weren’t the only conditions cited. Inspectors described eroding slopes, unstabilized ditches and sediment basins, missing features on the project’s pollution-control map, and bare ground directly beside Davis Creek. A West Virginia inspection in March 2025 recorded problems in many of the same control categories.

The resulting consent agreement proposes a $98,000 penalty against Kokosing Construction Company, the project’s stormwater permit holder. The state Department of Highways owns the site.

The Facts

Kokosing has been engaged since at least 2022 in widening an approximately 1.7-mile section of Jefferson Road, also known as West Virginia Route 601, in South Charleston. The project runs from U.S. Route 119 north to MacCorkle Avenue.

Stormwater from the construction site discharges into Davis Creek, which connects to the Kanawha River. Kokosing obtained coverage under West Virginia’s construction stormwater general permit, initially effective December 3, 2020 and reissued effective June 26, 2024. The permit is scheduled to expire April 5, 2029.

The West Virginia Department of Environmental Protection, or WVDEP, administers the water-discharge permitting program in the state. EPA retains authority to enforce permit requirements under the federal Clean Water Act.

$98,000 Proposed civil penalty in the consent agreement
5 Categories of permit violations alleged by EPA
15+ Drop inlets EPA said had damaged or insufficient protection
3 WVDEP notices of violation issued from 2022 through 2025

How the Stormwater Controls Were Supposed to Work

Construction stormwater permits regulate runoff from disturbed ground. At this site, Kokosing was required to maintain a Stormwater Pollution Prevention Plan, commonly called a SWPPP. The plan’s map was supposed to identify access roads and stormwater structures so the controls on the ground could be inspected and maintained against an accurate plan.

The permit also required β€œbest management practices,” or BMPs. Here, that term covers physical and operational controls such as silt fencing, sediment traps, stabilized ditches, inlet protection, seeding, mulching and designated concrete-washout areas. Their practical purpose is to reduce erosion and keep sediment or other construction material from moving through the site’s drainage system.

What Inspectors Documented

EPA organized its case into five counts. Each remains a factual allegation under the settlement’s terms, not an admission by Kokosing.

Alleged violation Inspection evidence cited in the agreement Period alleged
EPA allegation
Inaccurate SWPPP
Three infiltration ponds and four site access points were missing from the pollution-prevention plan’s map. At least May 14 to June 17, 2024
EPA allegation
Inlet and outlet protection
EPA reported more than 15 drop inlets with damaged or insufficient protection. WVDEP later cited sediment buildup and unprotected inlets on the project’s north end. At least May 14 to July 30, 2024, and March 4 to April 10, 2025
EPA allegation
BMP maintenance
Inspectors cited damaged silt fencing, overwhelmed perimeter controls, impaired rock ditch checks, inadequately stoned access points, eroding ditches and concrete outside a proper washout. At least May 14 to July 30, 2024, and March 4 to April 10, 2025
EPA allegation
Site stabilization
EPA described slopes, ditches, conveyance areas, infiltration basins and sediment basins needing vegetation, grading or other stabilization. WVDEP later rated stabilization practices unsatisfactory. At least May 14, 2024 to July 23, 2025
EPA allegation
Vegetative buffer
Inspectors observed bare areas beside waterways, including an unstabilized area directly abutting Davis Creek. The permit required a minimum 50-foot natural vegetative buffer. At least May 14, 2024 to July 23, 2025
The agreement doesn’t document a single missed formality. It describes failures across the site map, drainage inlets, perimeter controls, soil stabilization, concrete handling and the buffer beside Davis Creek.

The Inspection Trail

WVDEP inspected the site on eight dates listed in the agreement. It issued three notices of violation. EPA’s May 2024 inspection added the federal enforcement record that eventually became the basis of the proposed penalty.

December 3, 2020

Kokosing’s initial coverage under the state construction stormwater permit became effective.

August 24, 2022 and May 4, 2023

WVDEP issued the first two notices of violation identified in the agreement.

May 14, 2024

EPA inspected the Jefferson Road project and recorded the conditions later cited across all five counts.

June and July 2024

Kokosing updated the SWPPP map, installed a straw mat beside Davis Creek and reported that inlet and outlet issues had been addressed.

March 4, 2025

WVDEP’s inspection report rated several controls unsatisfactory, including perimeter controls, rock-check ditches, drop-inlet protection and stabilization. The state issued a third notice of violation.

April through July 2025

Kokosing reported cleaning inlets, installing new controls, fixing perimeter controls and reseeding affected areas, including work on July 22 and 23.

June 4, 2026

The respondent’s environmental director signed the supplied consent agreement on Kokosing’s behalf.

What Was at Stake Downstream

The permit identifies Davis Creek as the immediate receiving water and connects it to the Kanawha River. That relationship explains why damaged inlet protection, exposed soil and a missing streamside buffer fall under the Clean Water Act permitting system.

The supplied agreement does not quantify sediment discharged into Davis Creek, report water-quality measurements, identify downstream cleanup costs or establish harm to residents or wildlife. It documents alleged failures to maintain the controls required to reduce that risk. The distinction matters: the enforcement case concerns permit compliance, not a quantified finding of downstream environmental damage.

Kokosing’s Response

The record describes a series of corrective actions. Kokosing updated the site map on June 17, 2024. It told EPA on July 30 that inlets and outlets had been addressed. A photograph showed a straw mat installed July 25 on the area directly beside Davis Creek, followed by additional seeding.

After the March 2025 state inspection, Kokosing reported that drop inlets on the north end had been cleaned, new controls installed and perimeter controls repaired. The company said it attempted reseeding several times, including hydroseeding steeper slopes, and that BMPs remained in place during that period.

Kokosing also certified, based on personal investigation and to the best of its knowledge and belief, that it was currently in compliance regarding the alleged violations. The agreement does not include an independent inspection after the final July 2025 reseeding date.

What the Agreement Would Resolve

Kokosing consented to a $98,000 civil penalty to settle EPA’s claims for the five alleged permit violations. Once effective, the agreement requires payment within 30 days. Kokosing waived its right to contest the allegations for this proceeding and its right to appeal the accompanying Final Order.

The settlement is narrow. It resolves only EPA’s civil-penalty claims for the specific violations listed in the agreement. It doesn’t modify Kokosing’s continuing obligation to follow federal, state and local law, and EPA reserves its authority to pursue other enforcement where legally available.

The supplied document also sets out steps that must occur before the deal takes effect. EPA must provide a 40-day public notice and comment period. The agreement and Final Order become effective 30 days after the appropriate EPA officials sign and the package is filed with the Regional Hearing Clerk.

Those procedural steps are not visible as completed in the supplied copy. The EPA enforcement director’s signature line, the Regional Judicial Officer’s Final Order signature line and the certificate-of-service signature line are blank. The document therefore supports describing the $98,000 resolution as proposed or pending, not as a demonstrated final and paid penalty.

What Remains Unresolved

The record leaves two different questions open. The first is environmental: it establishes the site’s drainage connection and describes alleged control failures, but it doesn’t measure what, if anything, reached Davis Creek or quantify an ecological effect.

The second is procedural. Kokosing signed the agreement, but the supplied copy doesn’t show whether public comments were received, whether EPA officials later signed and filed the Final Order, or whether the penalty became due and was paid.

What a Legitimate Fix Looks Like

Editorial analysis

The alleged failures identify the remedy without requiring a new compliance theory. The project map must match the structures and access routes on the ground. Inlets, silt fencing, ditch checks and perimeter controls must remain functional rather than merely installed. Disturbed slopes and basins need stable cover, and the required buffer beside Davis Creek must become established rather than depend on repeated attempts that fail to germinate.

The key test is sustained performance. A repair reported after one inspection doesn’t establish that controls remained effective through the rest of the project. Later inspections are what can verify the compliance Kokosing certified.

What to Watch

  • EPA Region 3: completion of the required public-comment process and any signed, filed Final Order.
  • Kokosing Construction Company: payment of the $98,000 penalty within 30 days if and when the agreement becomes effective.
  • EPA and WVDEP: any later inspection record confirming whether stabilization, inlet protection, perimeter controls and the Davis Creek buffer remained compliant.

The supplied record ends before those events. It cannot establish that the proposed penalty became legally due, that Kokosing paid it, or that a later inspection verified the company’s compliance certification.

The source document for this investigation is attached below.

Aleeia
Aleeia

I'm Aleeia, the creator of this website.

I have 6+ years of experience as an independent researcher covering corporate misconduct, sourced from legal documents, regulatory filings, and professional legal databases.

My background includes a Supply Chain Management degree from Michigan State University's Eli Broad College of Business, and years working inside the industries I now cover.

Every post on this site was either written or personally reviewed and edited by me before publication.

Learn more about my research standards and editorial process by visiting my About page

Articles: 2207