George Industries Agreed to an $82,700 Penalty Over Hazardous-Waste Findings

Hazardous waste enforcement

George Industries Agreed to an $82,700 Penalty Over Hazardous-Waste Findings

EPA determined that the company failed federal and New York requirements governing hazardous-waste safety and storage at an aircraft-parts plant in Endicott. The settlement imposes a penalty, but George Industries neither admitted nor denied EPA’s findings.

Evidence note: This account is based on the supplied EPA Consent Agreement and Final Order. The document contains EPA findings and a negotiated settlement, not a merits hearing in which the allegations were adjudicated. It does not provide a filing date for the final order or proof that the penalty has been paid.

At an Endicott factory producing aircraft parts, a brazing process left behind salt sludge containing sodium fluoride, lithium and potassium. EPA classified that sludge as hazardous waste. When inspectors examined the facility, the agency later determined that George Industries had failed storage and safety requirements that made the difference between lawful short-term accumulation and operating an unpermitted hazardous-waste storage facility.

The company settled the case by consenting to an $82,700 penalty, waiving its right to contest or appeal the final order and committing to follow hazardous-waste rules going forward. Its agreement did not amount to an admission of EPA’s underlying findings.

$82,700Civil penalty George Industries agreed to pay within 30 days of the order’s filing date
100 to 1,000 kgAverage monthly range of non-acute hazardous waste identified by EPA, with both endpoints excluded
WeeklyMinimum frequency for future inspections of container-storage areas specified in the settlement

The permit exception came with conditions

EPA classified George Industries as a small quantity generator. That category can allow hazardous waste to be accumulated for up to 180 days without a storage permit, but only if the generator satisfies the applicable conditions.

According to EPA, George Industries did not meet those conditions. The agency determined that the company failed to minimize the possibility of a fire, explosion or unplanned release that could threaten people or the environment. EPA also found that its hazardous-waste storage did not satisfy the rules for permit-free accumulation.

Step 1

Manufacturing

The plant used a brazing process to manufacture aircraft parts.

Step 2

Waste generated

The process produced salt sludge that EPA identified as hazardous waste.

Step 3

Conditional accumulation

A small quantity generator may accumulate waste without a permit only by meeting required conditions.

Step 4

EPA conclusion

Because the conditions were not met, EPA treated the facility’s storage as unpermitted.

Conceptual summary of the regulatory mechanism described in the consent order. It does not represent measured quantities or an actual release.

The order states that George Industries had neither sought nor received interim status or a permit to treat, store or dispose of hazardous waste at the facility. EPA concluded that once the company failed the conditions for permit-free accumulation, it was not authorized to store hazardous waste there for any length of time.

“Neither admits nor denies the EPA’s Findings of Fact and Conclusions of Law.”George Industries’ stated position in the consent agreement

Why preventive rules matter even without a documented spill

The safeguards cited in the order are designed to operate before an emergency. Requirements for proper storage, emergency coordination, response information and routine container inspections reduce the chance that a deteriorating container or an operational problem turns into a larger event.

That distinction matters. EPA’s order supports a finding of regulatory noncompliance and unmanaged risk. It does not establish that the feared consequences actually occurred. Claims about illness, property damage or environmental contamination would go beyond the supplied evidence.

The settlement nevertheless makes the practical concerns visible. George Industries must have an emergency coordinator available at all times, post emergency and spill-response information next to the telephone, and inspect container-storage areas at least weekly for leaks and deterioration.

  • Prevent releasesMinimize the possibility of fire, explosion or sudden and non-sudden releases that could threaten health or the environment.
  • Maintain emergency coverageKeep an emergency coordinator available at all times.
  • Post response detailsDisplay coordinator contacts, equipment locations and the fire department number where required.
  • Inspect containersCheck storage areas at least weekly for leaks, corrosion and deterioration of containers or containment systems.

The agreement says that, as of its signature and to the best of its knowledge and belief, George Industries certified that the facility complied with applicable RCRA requirements. That is the company’s certification in the settlement, not an independent inspection result documented by the order.

From inspection to settlement

November 13, 2023
EPA inspected the Endicott facility for compliance with federal and authorized New York hazardous-waste regulations.
January to April 2024
EPA sent a combined notice of violation and information request on January 22. After requesting an extension, George Industries submitted a certified response on April 19.
April 16, 2025
EPA issued a notice of potential violations and an opportunity to confer.
June 2025 to April 2026
EPA and the company negotiated and exchanged additional information.
September 2, 2026
The respondent signature field in the supplied agreement identifies this date. The order’s separate filing date, which controls when it becomes effective, is not provided in the supplied copy.

What the $82,700 settlement resolves

The penalty resolves George Industries’ liability for federal civil penalties concerning the violations described in the settlement. It does not erase the company’s continuing duty to comply with federal, state and local hazardous-waste laws.

The document also preserves EPA’s ability to pursue other appropriate remedies or criminal sanctions for legal violations. It states that the settlement would not protect the company if it made material misrepresentations or supplied materially false information during the proceeding.

The legal status of the core claims
Hazardous-waste generationEPA identified the brazing-process sludge as hazardous waste and classified the plant as a small quantity generator.
Safety and storage failuresOfficial EPA findings contained in the consent order, but neither admitted nor denied by George Industries.
Civil penaltyGeorge Industries consented to an $82,700 assessment, payable within 30 days after the final order is filed.
Payment statusThe supplied document does not establish whether payment has occurred.
Actual harmNo spill, fire, explosion, exposure, contamination or injury is documented in the order.

The agreement says it becomes binding when filed with EPA Region 2’s Regional Hearing Clerk. Because the supplied copy does not give that filing date, it does not establish the payment deadline as a calendar date.

What remains unresolved in the public record supplied here

  • The final order’s filing and effective date.
  • Whether George Industries paid the penalty within the required period.
  • Whether EPA independently verified the company’s certification of current compliance after the settlement.
  • The specific facility conditions behind EPA’s broader finding that the company failed to minimize the possibility of fire, explosion or release.

A conditional privilege, not a blanket exemption

The settlement turns on a regulatory line that can disappear when its safeguards are ignored. George Industries’ generator status could permit limited accumulation without a storage permit, but that privilege depended on compliance with the conditions attached to it. EPA determined that the conditions were not met and treated the resulting storage as unauthorized.

That is the established accountability in this record: an $82,700 civil penalty, enforceable future obligations and a waived right to challenge the order. What the document does not establish is equally important. It does not show that hazardous waste escaped the plant or injured anyone, and the company did not admit EPA’s findings.

Source: U.S. Environmental Protection Agency Region 2, Consent Agreement and Final Order, In the Matter of George Industries, LLC, Docket No. RCRA-02-2026-7111. The supplied copy does not state the Regional Hearing Clerk filing date or document payment of the assessed penalty.
Aleeia
Aleeia

I'm Aleeia, the creator of this website.

I have 6+ years of experience as an independent researcher covering corporate misconduct, sourced from legal documents, regulatory filings, and professional legal databases.

My background includes a Supply Chain Management degree from Michigan State University's Eli Broad College of Business, and years working inside the industries I now cover.

Every post on this site was either written or personally reviewed and edited by me before publication.

Learn more about my research standards and editorial process by visiting my About page

Articles: 2352