How Elmore’s Gravel Giant Drowned 1,665 Acres of Alabama’s Wetlands
What Happened: A Mining Company Buried Alabama’s Wetlands and Called It Business
Elmore Sand & Gravel, Inc. operated a massive sand and gravel extraction operation on approximately 1,665 acres in Elmore County, Alabama, positioned just north of the city of Elmore, straddling Marion Spillway Road. The site sits near coordinates 32.568° N, 86.342° W. Over years of operation, the company discharged pollutants, specifically dredged and fill material, directly into waters and adjacent wetlands that are protected under the Clean Water Act, and it did so without authorization.
- The Clean Water Act, specifically Section 301(a), 33 U.S.C. § 1311(a), makes it unlawful to discharge pollutants into waters of the United States without a valid permit. Elmore Sand & Gravel had no such permit for the discharges at issue.
- Sections 402 and 404 of the CWA govern the two permit types relevant here: Section 402 covers general pollutant discharge (the National Pollutant Discharge Elimination System), and Section 404 covers the discharge of dredged or fill material into navigable waters and wetlands. The company was operating in violation of both.
- The federal complaint, filed January 17, 2025, alleged that the discharges were ongoing at the time of filing, not merely historical. The company was still polluting when the lawsuit landed.
- A portion of the 1,665-acre site is leased from the Alabama Department of Corrections, meaning a state government agency was a landlord to an operation that was actively degrading protected wetlands on that state-owned land.
- Settlement negotiations between the U.S. government and Elmore Sand & Gravel began “years before” the complaint was filed, per the decree itself. The company had advance knowledge that federal enforcement was coming, and the pollution continued anyway.
- Mortar Creek, a named waterway running through the site, is specifically identified as requiring stream stabilization and remediation under the resulting Consent Decree, signaling that the creek’s ecology was materially damaged by the company’s operations.
The Deal They Got: Zero Dollars in Penalties, Years to Fix It
The Consent Decree entered in this case is, functionally, an agreement that Elmore Sand & Gravel does not have to pay any civil penalty if it completes the required cleanup. The penalty is held in abeyance, not imposed. Here is exactly what the company was required to do, and on what timeline.
Stream Stabilization and Remediation of Mortar Creek
- Within 30 days of the decree’s effective date, the company must submit a remediation plan for Mortar Creek consistent with a Design Brief prepared by 5 Smooth Stones Restoration PLLC, originally transmitted to EPA on September 27, 2023, and again October 4, 2023, with corrections on February 28, 2024.
- The plan must target contractor selection beginning in early Spring 2025, with remediation work scheduled across 2025 through 2027. That is at minimum two to three years of work before the creek may be stabilized.
Stormwater and Wastewater Management
- Within 30 days of the effective date, the company must submit a stormwater and wastewater management plan consistent with TTL, Inc.’s 100% Plans Submittal, transmitted to EPA on October 4, 2023.
- This plan covers the ongoing management of industrial runoff from the mining and processing operations across the site, which the decree acknowledges must continue to fund the cleanup.
Wetlands Enhancement
- Within 30 days, the company must submit a plan for the enhancement of approximately seven acres of degraded wetlands, consistent with December 2024 correspondence between the parties.
- Seven acres of “enhancement” against a site where 1,665 acres of real property experienced unauthorized discharges represents a fraction of a percent of the total impacted area receiving direct restoration effort.
Wetlands Mitigation Credits
- Within 60 days of the effective date, the company must propose the purchase of eight wetlands mitigation credits from the McLemore Mitigation Bank, or from other Corps-approved mitigation banks if McLemore lacks sufficient credits.
- The actual purchase must be completed within 15 days after EPA approves the proposal, but no sooner than 90 days after the effective date.
- Mitigation credits are, in plain terms, a mechanism where a company pays into an ecological restoration fund elsewhere to offset damage it caused here. The company does not restore the specific wetlands it destroyed; it funds restoration somewhere else entirely.
Permanent Land Preservation
- Within 30 days, the company must submit a plan to preserve approximately 131 acres, including all delineated wetlands, delineated open water areas, and a 200-foot buffer along Mortar Creek, in perpetuity as “purely natural.”
- The preservation is enforced through a restrictive covenant that runs with the land and binds any future owner, including successors and assigns. The United States retains the permanent right to enter and inspect this 131-acre area even after the consent decree terminates.
- The 131-acre preservation area was identified on a map prepared by TTL, Inc. in December 2024. The map and the underlying correspondence were treated as settlement confidential, meaning the public does not have automatic access to the documents that defined exactly what land was being protected.
Five-Plus Years of Monitoring
- The company must fund and conduct monitoring, adaptive management, and maintenance for a minimum of five years after the completion of stream, wetlands, and stormwater work, and five years after the restrictive covenant is recorded.
- If the company fails to meet environmental performance criteria in year five, monitoring continues indefinitely until it does. Semi-annual reports are due to both DOJ and EPA every July 31st and January 31st for the life of the decree.
— Consent Decree, Paragraph 11
The Non-Financial Ledger: What the Lawyers Didn’t Put a Price On
There is no dollar amount in this consent decree for what was lost. The government calculated what Elmore Sand and Gravel could afford to pay, accepted the argument that the company needed to keep mining to fund its own cleanup, and structured a deal around cash flow projections. That is the financial ledger. This is the other one.
The 1,665 acres described in this case is not a number on a spreadsheet. It is a living system, or it was. Wetlands in Alabama’s Black Belt and surrounding regions are not scenic backdrops. They are filtration infrastructure. They absorb floodwater that would otherwise pour into the homes of people who cannot afford flood insurance. They process nitrogen and phosphorus from agricultural runoff before it reaches the drinking water supply. They shelter juvenile fish, amphibians, and migratory birds in a state that has some of the highest freshwater biodiversity in North America. When a gravel company fills those wetlands with dredged material without a permit, it does not just break a law. It removes services from communities that never knew they depended on them until they were gone.
Mortar Creek, the waterway threading through this site, now requires formal stream stabilization and remediation under court order. That language, clinical as it sounds, describes a creek that was destabilized. Banks eroded. Sediment loads increased. The creek’s geometry changed. The biological communities that lived in that specific stretch of water, communities assembled over decades of ecological succession, were disrupted or destroyed. A restoration plan written in 2023 by consultants and approved by EPA cannot restore what existed in that creek before the gravel machines arrived. It can build something that resembles it, if the monitoring targets are met, if the contractor performs, if the adaptive management triggers are hit. Those are a lot of ifs across a five-year minimum watchlist.
Then there is the Alabama Department of Corrections. The decree acknowledges, in a single understated paragraph, that part of the 1,665-acre site is leased from the Alabama Department of Corrections, which “is neither a party to the Complaint nor this Decree but which owns a portion of the Site.” Read that carefully. Alabama taxpayers, through the state’s prison system, own land that a private gravel company was using. That private company illegally polluted protected wetlands on land that ultimately belongs to the public. The Alabama Department of Corrections manages land on behalf of the people of Alabama, including the incarcerated people held within that system who have no voice in how state-owned land is used or degraded. None of them were made parties to this lawsuit. None of them will see remediation funds. None of them were consulted when settlement confidential correspondence was exchanged over years of negotiations.
The decree also quietly notes that documents central to the settlement, including the Design Brief for Mortar Creek restoration, the Stormwater/Wastewater Management plans, and the December 2024 correspondence that defined exactly what 131 acres would be preserved in perpetuity, were all treated as “settlement confidential.” The consent decree instructs that future versions of these plans “shall not be marked or treated as settlement confidential,” but that protection arrives after the most critical decisions were made behind closed doors. The public had no seat at the table when the shape of this deal was determined. They received a 30-day public comment window after the fact, once the papers were already signed and the die was cast.
Seven acres of wetland enhancement is what the company owes against a site where unauthorized discharges impacted a footprint of 1,665 acres. Eight mitigation credits, purchased from a bank somewhere else in the state, represent the monetary offset for destruction that happened here, in Elmore County, affecting this creek, these soils, these communities downstream. The people who live along the waterways fed by Mortar Creek did not choose this trade. They were not asked.
Legal Receipts: What the Decree Actually Says, Word for Word
These are direct quotations from the federal Consent Decree, Case No. 2:25-cv-60. No paraphrasing. No editorializing. Read the language and draw your own conclusions.
“The Complaint alleges that Defendant, without authorization, discharged and is continuing to discharge pollutants to waters and adjacent wetlands covered by the CWA located within what the Complaint refers to as the ‘Site,’ i.e., approximately 1,665 acres of real property in Elmore County, Alabama.”
- The government’s own complaint, incorporated into this decree, states that the discharges were ongoing at the moment the lawsuit was filed in January 2025. The company did not stop polluting when it learned federal action was coming.
- The word “continuing” is legally significant. It rules out any argument that this was a historical violation that had been self-corrected. The EPA was suing a company that was actively in violation of the Clean Water Act on the day the papers were filed.
“Although the United States requests in its Complaint that the Court award a civil penalty, at the time of the Parties’ execution of this Consent Decree, the United States has not assessed or requested that Defendant pay any amount of a civil penalty. Any civil penalty award for the United States’ claims alleged in the Complaint is held in abeyance pending Defendant’s timely completion of the mandatory injunctive relief required by this Decree. Upon Defendant’s timely completion of the mandatory injunctive relief required by this Decree, no such award shall be made.”
- The penalty is not deferred for collection later. It is eliminated entirely upon completion. The company owes nothing in fines if it finishes the cleanup on schedule.
- The government’s justification for this arrangement, buried in the “whereas” clauses, is that the company submitted evidence about “the limits of Defendant’s cash flow and ability to satisfy the financial aspects of any judgment.” The company argued it was too important to fine, and the government accepted that argument.
“Defendant contends that its continued mining, processing, and rail loadout operations on or in the vicinity of the Site are necessary for Defendant to support its implementation of the mandatory injunctive relief set forth in this Consent Decree, and Defendant has submitted evidence to the United States regarding the limits of Defendant’s cash flow and ability to satisfy the financial aspects of any judgment in this case.”
- The company is permitted to continue the industrial operations that created the environmental damage, on the grounds that those operations generate the revenue needed to fund the cleanup of that damage. The polluting operation funds the pollution remedy. The machine keeps running.
- There is no provision in the consent decree requiring independent financial verification of these cash flow claims. The government accepted the company’s self-reported financial evidence.
“Defendant represents that it intends to comply fully with this Consent Decree, and that it has made, is making, and will make all best and reasonable efforts (and has documented, is documenting, and will document all such efforts) to secure post-lease permission from Defendant’s lessor (Alabama Department of Corrections, which is neither a party to the Complaint nor this Decree but which owns a portion of the Site) to implement the mandatory injunctive relief obligations.”
- The Alabama Department of Corrections owns land within the contaminated site and has never been made a party to this case. Cleanup on state-owned land depends on post-hoc lease negotiations between the company and the prison system, not a court order directed at the state.
- If the Alabama Department of Corrections declines to grant access, the consent decree provides only that the parties will “confer about potential resolutions” and may develop “alternative and equivalent relief.” There is no guarantee that the state-owned portion of the site will be remediated under these terms.
“The mandatory injunctive relief plans referenced in Paragraphs 13 and 14 of this Consent Decree, in particular, are the result of the Parties’ (and their environmental consultants’) good faith, closely coordinated, and years-long efforts to meet injunctive relief objectives in consideration of Defendant’s ability-to-pay capability.”
- The remediation scope was designed around what the company could afford, not around what the ecosystem requires. The ecological standard was subordinated to the corporate financial constraint from the beginning of negotiations.
- The phrase “years-long efforts” confirms that while negotiations continued, discharges also continued. The remediation plan was being designed while the damage it describes was still being caused.
Societal Impact Mapping: Who Pays the Price When a Gravel Company Gets a Pass
Environmental Degradation
The documented harms to Alabama’s natural environment are specific, named, and verified by federal agency review.
- Mortar Creek, a named tributary running through the 1,665-acre site, was destabilized to the point that a court order now mandates formal stream stabilization and remediation. A creek requiring court-ordered stabilization has experienced altered hydrology, increased erosion, and damaged aquatic habitat.
- Wetlands within the site were subjected to unauthorized fill material, which by definition kills the hydrological and biological functions those wetlands perform. Once filled, wetland functions including flood buffering, water filtration, and habitat provision do not return automatically; they require active, years-long restoration.
- The degraded wetlands specifically identified for “enhancement” cover approximately seven acres. These are wetlands already so damaged that enhancement, rather than merely protection, is required. The federal government’s own consultants identified them as requiring active intervention to recover basic ecological function.
- The 200-foot buffer zone required along Mortar Creek, codified in the preservation plan, signals that the creek’s riparian zone was compromised. Riparian buffers filter pollutants before they reach the waterway and stabilize stream banks. Their formal designation as a protected area indicates they could no longer be trusted to function without legal protection.
- The fill material that was placed at the site before the complaint was filed is authorized, under Nationwide Permit 32, to “remain in place regardless of Site ownership.” This means some of the unauthorized fill will never be removed. It is permanently embedded in the landscape of this wetland system.
- Elmore County sits within the Mobile-Tensaw River Delta watershed region, one of the most biodiverse freshwater systems in North America. Wetland destruction upstream affects species assemblages, water quality, and ecological connectivity across a region that extends far beyond the 1,665-acre site.
Public Health
Wetland destruction translates directly into public health risk for communities downstream and in the floodplain. The harms here are measurable even if the decree assigns no dollar value to them.
- Wetlands adjacent to Mortar Creek function as natural flood control. When fill material is dumped into wetlands, their capacity to absorb storm surge and floodwater is reduced. Communities downstream in Elmore County and along the Alabama River drainage face elevated flood risk as a direct consequence of reduced wetland absorptive capacity, even if they never learned the cause.
- Unauthorized discharges of dredged and fill material increase suspended sediment in connected waterways. Elevated sediment loads degrade drinking water source quality, increase water treatment costs for municipal systems, and reduce dissolved oxygen in waterways, stressing fish populations that communities rely on for food and recreation.
- Industrial stormwater runoff from gravel mining operations can carry elevated concentrations of heavy metals, hydrocarbons, and fine particulates into connected waterways. The decree’s explicit requirement for a stormwater and wastewater management plan confirms that the site’s industrial runoff was not being adequately controlled before federal enforcement action.
- Elmore County has a predominantly rural population. Rural communities typically have higher rates of dependence on private wells and on fishing as a food source. Contamination events that would merely raise a municipal water treatment bill in an urban area can directly affect the drinking water and dietary protein sources of rural households.
Economic Inequality
The structure of this settlement is itself an expression of economic inequality: who pays, who is protected, and who is left to absorb the risk.
- Elmore Sand and Gravel successfully argued that its cash flow limitations should define the scope of environmental remediation. Companies with fewer financial resources, specifically the working-class and rural residents downstream of this site, have no equivalent mechanism to argue that their financial limitations should define what level of environmental degradation they are required to accept.
- The company was permitted to continue mining operations, generating revenue from the same site it was under court order to clean up. Individual residents who damage protected wetlands, even inadvertently and at a fraction of this scale, do not receive the option to continue the activity that caused the damage while the remediation is planned.
- Mitigation credits, the mechanism by which eight credits are purchased from the McLemore Mitigation Bank, fund wetland restoration at a site other than the one that was damaged. Any ecological benefit accrues to a location determined by the bank’s geography, not to Elmore County, not to Mortar Creek, and not to the communities that live adjacent to the contaminated site.
- Settlement documents including the Design Brief, Stormwater/Wastewater Plans, and December 2024 correspondence were treated as settlement confidential during negotiation, meaning the people most affected by the contamination had no access to the technical documents defining what cleanup was planned for their watershed.
- The Alabama Department of Corrections, as landlord to the contaminated site, manages state-owned assets that were degraded by a private tenant. The department’s incarcerated population and the communities surrounding Alabama’s prison facilities bear no responsibility for this environmental damage and receive no direct benefit from the remediation payments that were avoided through the consent decree structure.
The “Cost of a Life” Metric: What $0 in Penalties Actually Means
8 Mitigation Credits Purchased
Eight credits from the McLemore Mitigation Bank offset damage to a nationally significant wetland system. The credits fund restoration somewhere else in Alabama, not in Elmore County, and not on Mortar Creek.
5+ Years of Monitoring
The company must fund monitoring, adaptive management, and maintenance for at least five years post-restoration. If performance criteria are not met in year five, monitoring continues indefinitely at company expense.
131 Acres Preserved Forever
A restrictive covenant preserves 131 acres in perpetuity, binding all future owners. The U.S. retains permanent right of entry to this area even after the decree terminates.
Mortar Creek: 2025–2027 Work Window
Contractor selection begins Spring 2025. Active stream stabilization and remediation work spans 2025 through 2027. The creek remains in its damaged state until then.
What Now: The Watchlist and How to Push Back
The consent decree entered in January 2025 is a court order, not a completed remediation. It contains dozens of deadlines, reporting obligations, and performance thresholds that must be monitored, reported on, and enforced over years. Here is who is responsible and how to hold them to it.
Corporate Accountability Targets
The source document does not identify individual executives by name within the decree text. Corporate accountability falls on the following roles and entities:
- Elmore Sand & Gravel, Inc., Defendant, Elmore County, Alabama. Contact for compliance correspondence routed through: bstabo@standardsand.com (as listed in the consent decree’s official notice section).
- The Alabama Department of Corrections, as the landowner of a portion of the contaminated site, holds leverage over whether remediation can proceed on state-owned land. Its failure to grant post-lease access would create a gap in cleanup coverage that the consent decree addresses only through informal negotiation.
Regulatory Watchlist
- U.S. Environmental Protection Agency, Region 4: The primary regulatory authority overseeing this consent decree. Rachel Earwood (earwood.rachel@epa.gov) and Matthew Hicks (hicks.matthew@epa.gov) are the named EPA contacts. EPA must approve all deliverables submitted by the company and can disapprove, conditionally approve, or require resubmission of any plan.
- U.S. Army Corps of Engineers, Mobile District: The Corps administers Section 404 permitting for dredge and fill activities. The Mobile District is specifically named in the decree as the agency through which Corps functions operate for this case. The Corps also maintains template forms for restrictive covenants that the company is directed to consult.
- U.S. Department of Justice, Environment and Natural Resources Division: DOJ’s Environmental Defense Section filed the complaint and is party to the decree. Andrew J. Doyle (andrew.doyle@usdoj.gov) and Martin F. McDermott (martin.mcdermott@usdoj.gov) are the named trial attorneys. The DOJ receives all semi-annual compliance reports directly.
- Alabama Department of Environmental Management (ADEM): The decree explicitly preserves ADEM’s authority to take permit actions under Section 402 of the CWA. ADEM is an independent state enforcement actor that can act regardless of the federal consent decree’s terms.
- U.S. District Court, Middle District of Alabama, Northern Division: The court retains jurisdiction over this consent decree for the life of the agreement. Any member of the public may access the court docket for Case No. 2:25-cv-60 through PACER (Public Access to Court Electronic Records) to review all filed documents, including semi-annual reports as they are submitted.
Specific Deadlines to Watch in 2025
- Within 30 days of effective date: Elmore S&G must submit plans for Mortar Creek remediation, stormwater/wastewater management, wetlands enhancement, wetlands preservation, and the monitoring and adaptive management framework. If these deadlines are missed, stipulated penalties begin accruing immediately at $500 per day, escalating to $3,000 per day after 60 days.
- Within 60 days of effective date: The company must submit its proposal for purchasing eight wetlands mitigation credits from the McLemore Mitigation Bank.
- Within 90 days of effective date: The actual credit purchase must be completed.
- July 31, 2025: First semi-annual compliance report due to DOJ and EPA. This report is a public filing and can be accessed through the court docket.
How to Act
- Access the court docket directly. Case No. 2:25-cv-60 in the U.S. District Court for the Middle District of Alabama is a public record. Use PACER (pacer.gov) to pull the filed complaint, the consent decree, and any future compliance reports the company submits. These documents belong to the public.
- Contact EPA Region 4. Written comments, concerns, or evidence of non-compliance related to this decree can be submitted to EPA Region 4 in Atlanta. Document any changes you observe in Mortar Creek or the surrounding wetlands with photographs, dates, and GPS coordinates and submit them to the named EPA contacts listed in the decree.
- Engage the Alabama Department of Environmental Management. ADEM has independent state enforcement authority that was explicitly preserved in this decree. Contacting ADEM with documented concerns about ongoing discharges or inadequate stormwater controls can trigger a separate state-level response that the federal consent decree cannot preempt.
- Support local environmental organizations operating in the Black Belt and Alabama River watershed. Groups monitoring water quality, wetland health, and ecological connectivity in central Alabama are the ground-level eyes on whether the remediation targets in this decree are actually being met. Material support, volunteer labor, and documentation sharing strengthens their capacity to hold corporate and regulatory actors accountable.
- Organize around the public comment window. The consent decree required a minimum 30-day public comment period after lodging with the court. If you are reading this during that window, written comments to the DOJ Environmental Defense Section create a formal record that the court must consider before entering the decree as final. If the window has passed, the next enforcement lever is the semi-annual reporting cycle.
- Document the Alabama Department of Corrections’ role. The state prison system’s land ownership within the contaminated site is a public interest issue that extends beyond environmental law. Alabama legislators, the state attorney general’s office, and prison oversight organizations should be made aware that state-owned land was used by a private gravel company for operations that resulted in a federal CWA enforcement action, and that the state agency was excluded from the lawsuit entirely.
Who Is Connected to This Case
The source document for this investigation is attached below.
The DOJ has a consent decree: https://www.justice.gov/enrd/media/1385246/dl?inline
The Department of Justice also has a legal complaint here: https://www.justice.gov/enrd/media/1385241/dl?inline
Explore by category
Product Safety Violations
When companies sell dangerous goods, consumers pay the price.
View Cases →Financial Fraud & Corruption
Lies, scams, and executive impunity that distort markets.
View Cases →


